CIP Projects List
Click Project Type For More Details
Master Projects List
CIP # | Project Name | Program Name | Category Name | Status | Phase | Start Date | End Date |
---|---|---|---|---|---|---|---|
1 | Water Supply Program - Quarry/Chattahoochee | Water | Water Supply | Complete | Close Out | 3/23/2014 | 12/30/2021 |
3 | RM Clayton WRC - Two Scroll Bowl Kits, Switch Gears, Emergency Generators | Wastewater | Water Reclamation Centers & Facilities | Complete | Construction | 12/21/2015 | 2/22/2019 |
4 | Hemphill/Chattahoochee WTP - Instrumentation & Controls System | Water | Water Supply | Inactive | Design | 10/11/16 | 9/8/2022 |
5 | Southeast Atlanta Green Infrastructure Initiative (SAGII) - Permeable Pavers | Wastewater | Watershed Protection | Complete | Construction | 07/30/2013 | 09/24/2019 |
6 | Southeast Atlanta Green Infrastructure Initiative (SAGII) - Capacity Relief Ponds | Wastewater | Watershed Protection | Inactive | Design | 12/2014 | 10/2021 |
7 | Custer Avenue Water Quality Control Facility - Additional Screens | CSO Facilities | CSO Facilities | Inactive | Design | 01/2014 | 12/30/2017 |
8 | Peachtree Creek Trunk Sewer Stabilization | Wastewater | Wastewater Collection | Complete | Construction | 11/11/2016 | 04/25/2022 |
9 | Upper Proctor Creek Sewer Capacity Relief - Mitchell Street Sewer (Project now a part of the Rodney Cook, Sr Park in Historic Vine City) | Wastewater | Watershed Protection | Inactive | Construction | 01/1/2016 | 04/1/2019 |
10 | Upper Proctor Creek Sewer Capacity Relief - Rodney Cook, Sr Park in Historic Vine City (Formerly known as Mims Park Pond) | Wastewater | Watershed Protection | Complete | Construction | 08/10/2016 | 05/07/2021 |
11 | SG3 Contract B Small Diameter Rehabilitation | Wastewater | Consent Decree | Complete | Construction | 04/20/2016 | 08/10/2020 |
12 | SG3 Contract C Small Diameter Rehabilitation | Wastewater | Consent Decree | Complete | Construction | 10/11/2016 | 04/30/2020 |
13 | SG3 Capacity Relief Projects - Ashby-Jett, Lower Proctor Trunk & Terrell Creek Trunk (Phase 2 and Niles Ave) | Wastewater | Consent Decree | Complete | Construction | 11/03/2015 | 05/06/2020 |
14 | SG4 Advanced Sewer Capacity Relief - Collier Road, Howell Mill Road & Woodward Way Outfalls | Wastewater | Consent Decree | Complete | Design & Construction | 12/1/2013 | 12/1/2019 |
15 | SG3 Contract D Small Diameter Rehabilitation | Wastewater | Consent Decree | Complete | Construction | 07/24/2017 | 06/30/2020 |
16 | SG4 Pipe Rehabilitation (SG4 Small Diameter Rehabilitation - Contract A) | Wastewater | Consent Decree | Active | Construction | 02/1/2018 | 12/05/2024 |
17 | RM Clayton WRC - Headworks | Wastewater | Water Reclamation Centers & Facilities | Complete | Construction | 08/10/2016 | 07/08/2018 |
18 | Utoy Creek WRC - Aeration Tanks/Slide Gates | Wastewater | Water Reclamation Centers & Facilities | Complete | Construction | 05/13/2014 | 04/30/2020 |
19 | RM Clayton WRC - Instrumentation & Controls Reliability Restoration | Wastewater | Water Reclamation Centers & Facilities | Complete | Construction | 08/12/2014 | 04/09/2020 |
20 | Peyton Center | General Support | Facilities Management | Active | Design | 01/14/2015 | 04/13/2026 |
21 | Hartsfield Jackson Manifold Improvements | Water | Water Distribution | Complete | Construction | 02/16/2018 | 03/02/2020 |
22 | RM Clayton Nutrient Recovery | Wastewater | Water Reclamation Centers & Facilities | Complete | Construction | 05/10/2018 | 03/06/2020 |
23 | Chattahoochee WTP Compliance Improvements | Water | Drinking Water Facilities | On Hold | Design | 1/25/2018 | 09/18/2025 |
24 | West Area Water Quality Control Facility Improvements | CSO Facilities | CSO Facilities | Active | Close Out | 03/01/2013 | 06/30/2023 |
25 | Nancy Creek Tunnel Shafts Odor Control | Wastewater | Wastewater Collection | Complete | Construction | 10/5/2016 | 1/26/2018 |
26 | West Area Water Quality Control Facility - Outfall | CSO Facilities | CSO Facilities | On Hold | Design | 08/10/2016 | TBD |
27 | Large Diameter Water System Rehabilitation & Replacement | Water | Water Distribution | Active | Planning | 07/01/2015 | 03/01/2018 |
28 | Asset Management Implementation & Planning | General Support | Support Services | Complete | Construction | 08/12/2016 | 07/25/2019 |
29 | Geotechnical Testing & Investigation | General Support | Support Services | Active | Construction | 07/03/2018 | 04/01/2024 |
30 | GDOT/IntraGovernment Agreements Utility Relocation | General Support | Support Services | Active | Design | 06/23/2014 | 09/29/2023 |
31 | Sanitary Sewer Repairs - Annual Contract | Wastewater | Consent Decree | Complete | Construction | 05/18/2016 | 09/16/2021 |
32 | Sewer Cleaning & Pipeline Assessment | Wastewater | Wastewater Collection | Inactive | Close Out | 08/12/2016 | 07/12/2022 |
33 | Asphaltic Concrete Pavement Milling & Resurfacing | General Support | Support Services | Active | Bid/Award | 10/22/2020 | 03/04/2022 |
34 | Facility Structural and Site Improvements | General Support | Facilities Management | Active | Project Management | 01/01/2019 | 12/31/2023 |
39 | Emergency Sewer Repairs | Wastewater | Wastewater Collection | Complete | Complete | 08/12/2016 | 07/12/2022 |
40 | Green Infrastructure Maintenance | Wastewater | Watershed Protection | Inactive | Inactive | 06/01/2017 | TBD |
43 | Plant Capital Maintenance - Small Capital | Wastewater | Water Reclamation Centers & Facilities | Active | Construction | 10/05/2016 | 01/23/2022 |
44 | Small Business Development Program | General Support | Support Services | Active | Project Management | 02/21/2017 | 12/31/2021 |
45 | Fleet Replacement | General Support | Support Services | Active | Project Management | 03/01/2018 | 12/29/2023 |
46 | Program Management | General Support | Support Services | Active | Project Management | 09/07/2017 | 04/28/2023 |
48 | Clear Creek West Sewer Improvements - Civic Center Vault | Wastewater | Watershed Protection | Complete | Complete | 09/26/2017 | 05/19/2019 |
49 | Clear Creek Chemical System Improvements (Bid Package 1) and System-wide Flow Monitoring | CSO Facilities | CSO Facilities | Complete | Construction | 02/28/2013 | 09/29/2019 |
50 | Downtown Water Storage Tank & Pump Station and Upgrades at Hemphill Pump Station | Water | Drinking Water Facilities | Active | Planning | 10/04/2016 | 06/30/2023 |
51 | Intrenchment Creek WRC Decommissioning/South River WRC Primary Clarifiers Replacement | Wastewater | Water Reclamation Centers & Facilities | Active | Construction | 05/31/2013 | 10/22/2024 |
52 | RM Clayton Supplemental Blowers | Wastewater | Water Reclamation Centers & Facilities | Complete | Construction | 06/15/2015 | 12/18/2017 |
53 | South River WRC Various Projects Group 1 | Wastewater | Water Reclamation Centers & Facilities | On-Hold | Planning | 06/04/2013 | TBD |
54 | Randall Hall Sewer Improvements | Wastewater | Wastewater Collection | Complete | N/A | 01/2013 | 12/2016 |
55 | Intrenchment Creek Viaduct Rehabilitation | Wastewater | Water Reclamation Centers & Facilities | Complete | Construction | 05/03/2017 | 12/15/2020 |
56 | Pump Stations Improvement: Philip Lee, Rebel Forest, Woodward Way 1 and 2, Cascade, NiskeyLake 1, Highlands, SR Industrial, Rivermeade, Bell South, Paul Avenue | Wastewater | Water Reclamation Centers & Facilities | On Hold | Planning | Varies | 03/24/2025 |
57 | Bolton Road Sewage Pump Station Rehabilitation | Wastewater | Water Reclamation Centers & Facilities | On-Hold | Design | 04/29/2019 | 07/27/2022 |
58 | East Area Water Quality Control Facility Improvements | CSO Facilities | CSO Facilities | Active | Construction | 02/28/2013 | 01/28/2024 |
59 | Distribution System Telemetry Improvements | Water | Water Distribution | On-Hold | Planning | 11/30/2018 | 02/27/2023 |
60 | Combined Sewer System Repair & Rehabilitation | Stormwater | Stormwater | Active | Bid/Award | 10/2016 | 09/1/2024 |
61 | Clear Creek West Green/Grey Infrastructure Initiative | Wastewater | Watershed Protection | Complete | Construction | 03/01/2015 | 09/30/2023 |
62 | RM Clayton WRC Sand Filter Media Change-out and Refurbishment | Wastewater | Water Reclamation Centers & Facilities | Complete | Construction | 04/06/2016 | 02/15/2019 |
63 | Upper Proctor Creek - Boone Boulevard Green Infrastructure | Wastewater | Watershed Protection | Complete | Construction | 11/30/2015 | 12/24/2020 |
64 | Utoy Creek WRC Improvements - Group 1 | Wastewater | Water Reclamation Centers & Facilities | On Hold | Construction | 11/04/2021 | 09/30/2027 |
65 | RM Clayton WRC Thickener Waste Activated Sludge Centrifuge | Wastewater | Water Reclamation Centers & Facilities | Complete | Construction | 12/28/2015 | 06/02/2017 |
66 | Flint River Sewage Pump Station Replacement | Wastewater | Water Reclamation Centers & Facilities | Inactive | Design | 12/02/2020 | 12/02/24 |
67 | Treatment Plant Facilities - Various Projects - Bid Pkg 2 of 6 (Utoy Creek WRC headhouse MCC's and I&C Improvements and Phillip Lee PS bar screens) | Wastewater | Water Reclamation Centers & Facilities | Complete | N/A | 04/2014 | 03/2018 |
68 | Hemphill WTP Compliance Improvements | Water | Drinking Water Facilities | On Hold | Design | 2/5/2018 | 02/04/2026 |
69 | Upper Proctor Creek Water Quality Facility | Wastewater | Watershed Protection | Inactive | Planning | 10/06/2016 | 09/05/2022 |
70 | Peachtree Creek - South Fork Green Infrastructure - Cheshire Bridge Road | Wastewater | Watershed Protection | Inactive | N/A | 10/01/2015 | 08/23/2023 |
71 | Water Quality Control Facilities Improvements Design | CSO Facilities | CSO Facilities | Complete | Design | 10/06/2016 | 01/14/2019 |
72 | RM Clayton Plant Entrance | Wastewater | Water Reclamation Centers & Facilities | Inactive | Design | 10/2016 | 09/05/2022 |
73 | RM Clayton Belt Filter Presses | Wastewater | Water Reclamation Centers & Facilities | Complete | Construction | 07/29/2016 | 07/24/2017 |
74 | RM Clayton Emergency Dewatering and Hauling | Wastewater | Water Reclamation Centers & Facilities | Complete | Construction | 01/18/2016 | 10/31/2016 |
76 | Hemphill Reservoir #1 Embankment Repair | Water | Water Supply | Active | Close Out | 04/30/2018 | 11/30/2022 |
77 | South River WRC Filter Refurbishment | Wastewater | Water Reclamation Centers & Facilities | Complete | Construction | 10/06/2016 | 09/05/2022 |
78 | Green Infrastructure Design Challenge (This $2.4M project is funded through the Municipal Option Sales Tax (MOST)) | Wastewater | Watershed Protection | Inactive | Construction | 05/01/2018 | 10/20/2023 |
79 | Municipal Option Sales Tax (MOST) Miscellaneous Stormwater & Drainage Improvements - Phases 1, 2 and 3 | Stormwater | Stormwater | Active | Construction | 12/1/2018 | 12/01/2020 |
80 | RM Clayton Digesters Improvements and Rehabilitation | Wastewater | Water Reclamation Centers & Facilities | Active | Design | 01/16/2018 | 12/23/2022 |
81 | Linear Asset Maintenance & Management Support | Water | Water Distribution | Active | Project Management | 02/05/2018 | 12/29/2023 |
82 | Cooperative Purchasing Agreement for Water Meter Installation & Replacement Services | Water | Water Distribution | Active | Construction | 02/06/2018 | 08/31/2023 |
83 | Annual Contract for Large Water Meter Installations | Water | Water Distribution | Complete | Construction | 9/23/2014 | 10/08/2021 |
84 | Annual Contract for Water Facilities Installations | Water | Water Distribution | Complete | Construction | 03/03/2015 | 12/01/2022 |
85 | Annual Contract for Large Meter Testing & Repair | Water | Water Distribution | Complete | Construction | 9/29/2016 | 4/10/2022 |
86 | Annual Contract for Testing & Analysis of Large Water Meters | Water | Water Distribution | Complete | Construction | 09/29/2016 | 05/10/2022 |
87 | Water System Master Plan Update | Water | Water Distribution | Complete | Planning | 04/09/2020 | 06/26/2020 |
88 | Wastewater Master Plan | Wastewater | Wastewater Collection | Complete | Planning | 04/09/2020 | 06/26/2020 |
89 | Southeast Atlanta Green Infrastructure Initiative (SAGII) Phase 3 – Connally Vault | Wastewater | Watershed Protection | Inactive | Planning | 07/01/2015 | 10/09/24 |