Water System Projects
Water Project
Project Name: Water Supply Program – Quarry/Chattahoochee
The project consists of a 10-foot diameter deep tunnel conveyance system that will connect the Chattahoochee River to CWTP, HWTP and a new 2.4 billion-gallon storage facility at the Quarry.
The scope of this project includes:
- New pump stations at HWTP and the quarry
- Ten (10) Pump Station and Flow Control Shafts
- Adits (Connecting tunnels)
Justification:
- Addresses Consent Decree requirements
- Enhances flow capacity of small diameter sewers
- Reduces inflow and infiltration or extraneous flows into the sewer system
- Increases protection of our receiving waters and reduces threat to public health and safety
Project Type: Water Supply
Project Start: 03/23/2014
Proposed Construction Start: 02/2015
Scheduled Completion: 12/30/2021
Project Budget: $367,800,000
Council District(s): Citywide
NPU(s): Citywide
Project Status / Phase: Complete / Close Out
Map: Link