Project Name: RM Clayton Plant Entrance
The entrance to the Chattahoochee Water Treatment Plant (WTP) and RM Clayton Water Reclamation Facility (WRF) sits at the intersection of Marietta Boulevard, Bolton Road, and Adams Drive. The goal of this project is to provide additional traffic safety and simplify the intersection.
The scope of this project includes:
- Closing the RM Clayton WRC/Chattahoochee WTP Road entrance
- Installing an upgraded security entrance at existing Coronet Way off Moore’s Mill
- Performing a study to evaluate utility conflicts, security concerns, and site restrictions
Justification:
- Improves public safety and traffic problems in the area
- Provides safer access for employees, contractors, and suppliers who access the facilities
NOTE: Design is complete. Project is on-hold until further evaluation
Project Type: Water Reclamation Centers and Facilities
Proposed Project Start: 10/1/2015
Proposed Construction Start: TBD
Scheduled Completion: 9/5/2022
Project Budget: $407,000
Council District(s): 2, 3, 4, 5, 6, 7, 8, 9
NPU(s): A, B, C, D, E, F, J, K, L, M, N, O, S, T, V, W
Project Status: Inactive / Design