Wastewater System
Wastewater System
Project Name: Randall Hall Road Sewer Improvements
Homes along Randall Hall were originally connected to a dry sewer. To address this issue, a storage tank was installed to collect the raw sewage and is being pumped out frequently to prevent further spills. A sewer extension is required to connect homes to the sewer system.
The scope of this project includes:
- Installing a sewer extension to the dry sewer located along Randall Hall
Justification:
- Provides connectivity for existing and future homes within the project area
- Alleviates the need for the storage tank that was placed on Randall Hall
- Improves service to the residents within the project area
- Installing a sewer extension to the dry sewer located along Randall Hall
Project Type: Wastewater Collection
Project Start: 01/12/2013
Proposed Construction Start: 08/09/2016
Scheduled Completion: 07/2018
Project Budget: $1,660,000
Council District(s): 9
NPU(s): D, G
Project Status / Phase: Complete