SG4 Advance Sewer Capacity Relief – Woodward Way Outfall
Collier Road Outfall Sewer Improvements Project
The Department is continuing the implementation of the Sewer Capacity Relief Program to upgrade its existing large diameter system to eliminate sanitary sewer overflows and capacity limitations. To accomplish this objective, the City is proposing system improvements for the existing Collier Road Outfall sewer.
Collier Road Outfall sewer located in the Peachtree Creek sewer basin. The outfall sewer services the Howell Mill & Collier Road area, East of I-75 North to Brookview Park. Based on hydraulic analysis, the sewer currently has capacity limitations.
The scope of this project includes:
Replacing existing outfall
Realigning of a portion of the sewer
Justification:
Provides adequate capacity to reduce sanitary sewer spills
Extends service life and improve flow conveyance
Addresses Consent Decree requirements
Project Type: Consent Decree Project Start: 11/03/2015 Proposed Construction Start: Varies Scheduled Completion: 09/01/2020 Project Budget: $7,922,000 Council District(s): Citywide NPU(s): Citywide Project Status / Phase: Complete / Design & Construction