This project will upgrade various outdated Distributive Control Systems (DCS) and Process Logic Controller (PLC) systems as well as add optical fibers and duct banks at the RM Clayton Water Reclamation Center (WRC). These systems monitor and control various process equipment and provide the interconnectivity required to treat wastewater to meet regulatory compliance permits.
The scope of this project includes:
Installing additional duct banks and fiber optic cables
Replacing input and output modules in various buildings
Upgrading and consolidating DCS control processors
Translating old databases for new control modules
Replacing PLCs at Incinerator Building and Blower Building
Installing new fiber network for Administration Building and various other buildings
Justification:
Removes and replace obsolete instrumentation and control equipment
Reduces corrective and emergency maintenance
Enhances system operational reliability
Facilitates compliance with regulatory requirements
Project Type: Water Reclamation Centers and Facilities Project Start: 08/12/2014 Proposed Construction Start: 09/2018 Scheduled Completion: 04/09/2020 Project Budget: $5,300,000 Council District(s): 2, 3, 4, 5, 6, 7, 8, 9 NPU(s): A, B, C, D, E, F, G, J, K, L, M, N, O, T, V Project Status: / Phase: Complete / Construction