The entrance to the Chattahoochee Water Treatment Plant (WTP) and RM Clayton Water Reclamation Facility (WRF) sits at the intersection of Marietta Boulevard, Bolton Road, and Adams Drive. The goal of this project is to provide additional traffic safety and simplify the intersection.
The scope of this project includes:
Closing the RM Clayton WRC/Chattahoochee WTP Road entrance
Installing an upgraded security entrance at existing Coronet Way off Moore’s Mill
Performing a study to evaluate utility conflicts, security concerns, and site restrictions
Justification:
Improves public safety and traffic problems in the area
Provides safer access for employees, contractors, and suppliers who access the facilities
NOTE: Design is complete. Project is on-hold until further evaluation
Project Type: Water Reclamation Centers and Facilities Proposed Project Start: 10/1/2015 Proposed Construction Start: TBD Scheduled Completion: 9/5/2022 Project Budget: $407,000 Council District(s): 2, 3, 4, 5, 6, 7, 8, 9 NPU(s): A, B, C, D, E, F, J, K, L, M, N, O, S, T, V, W Project Status: Inactive / Design