Project Name: Nancy Creek Tunnel Shafts Odor Control
The Department aims to restore full design capacity of the Nancy Creek Tunnel, providing sustainable relief from sanitary sewer overflows for the Nancy Creek basin community. Three construction shafts were constructed as part of the Nancy Creek Tunnel project. R.M. Clayton and Johnson Ferry Road tunnel shafts anchor the tunnel line, with an intermediate shaft located at Roswell Road. One intake is located at each of the construction shaft sites. The tunnel lift station is located at the end of the tunnel, inside the R.M. Clayton facility.
The scope of the project includes:
Modifying existing odor equipment located at two, tunnel drop shafts
Reconditioning odor control equipment (scrubbers) to original factory specifications
Justification:
Reduces odors in area surrounding drop shafts
Extends service life of odor control assets
Project Type: Wastewater Collection Project Start: 10/05/2016 Proposed Construction Start: 10/05/2016
Scheduled Completion: 01/26/2018 Project Budget: $1,068,240 Council District(s): 7, 8, 9 NPU(s): B Project Status / Phase: Complete / Construction