The water system includes two raw water reservoirs located in northwest Atlanta with a combined storage capacity of approximately 525 million gallons, providing about five days of storage for water treatment and distribution. The reservoir east of Howell Mill Road, Hemphill Reservoir #1, provides approximately one-third of the reservoirs’ total storage capacity but is currently not in service. In order to provide enough storage capacity to the constituency and reduce the threat of water deficiency, the goal of this project is to return the Hemphill Reservoir #1 to active service.
The scope of this project includes:
Constructing a permanent drainage system
Repairing minor embankment erosion and revetment repairs to both reservoirs
Implementing corrective action required by the Georgia Department of Natural Resources
Justification:
Supports economic development
Increases storage for water treatment and distribution
Enhances system operational reliability to include system redundancy
Reduces corrective and emergency maintenance of existing raw water delivery
Project Type: Water Supply Project Start: 04/30/2018 Proposed Construction Start: 7/7/2022 Scheduled Completion: 11/30/2022 Project Budget: $3,220,000 Council District(s): Citywide NPU(s): Citywide Project Status / Phase: Active / Close out